Fixing the NSW Housing Crisis: Fast Approvals and Factory-Built Homes.

NSW is building half the homes it promised. Strategist and engineer Dainu Devis sets out a five-move plan built on fast approvals, modular construction and a guaranteed order book, with global evidence.



NSW promised homes. It’s delivering half.

Do the maths.

The problem in numbers

  • Target: about 377,000 homes by mid-2029. That’s more than 88,000 a year.
  • Delivered: 44,700 completions in the year to March 2026, per the Property Council.
  • Pipeline: commencements fell 29 per cent in the March quarter.
  • Rent: Sydney units hit a record $780 a week (Domain, September 2026).
  • Affordability: 7 of 12,155 listings in Sydney and the Illawarra were affordable for a single person on the minimum wage (Anglicare, March 2026).

Young people are doing everything right and still locked out. That’s a broken promise between generations.

Where it jams

Approval speed depends on your postcode. Local development applications averaged 60 days in 2025-26. Complying development, which follows set rules, averaged 20 (Department of Planning). The fastest council took 18 days. The slowest took 174.

Big projects stall too. The Housing Delivery Authority had declared 493 proposals, about 153,000 homes, by 31 July 2026. Only 14 were approved. That’s under 2 per cent.

Then there’s the build itself. Australia still builds most homes by hand, on site, in the rain. Offsite construction is just 3 to 5 per cent of new housing (Treasury, October 2026).

What the world has tried

Singapore. Since 2014, selected government land sales must use prefabricated volumetric construction. Productivity gains of up to 40 per cent. Up to 30 per cent less time per floor (Building and Construction Authority).

Tasmania. ModHomes has delivered 280+ homes, with 271 more coming. Units spend 8 to 10 weeks in the factory and save 3 to 4 months per project (Pulse Tasmania, August 2026).

New Zealand. MultiProof lets one approved design get consent in 10 working days, anywhere. But imported container units in Rotorua cost over NZ$630,000 each (NZ Herald). Modular isn’t magic.

United Kingdom. Ilke Homes collapsed in 2023 owing about £319 million (Housing Today). Factories die when orders stop.

The lesson is clear. Speed comes from repetition. Repetition needs a steady pipeline.

The four tests

  • Welfare: more homes, sooner, at lower cost. Rents ease when supply rises.
  • Example: government puts its own land and its own social housing orders first.
  • Stewardship: a fixed design approved once saves every council assessing it again.
  • Delivery: completions reported every quarter. No hiding.

The fix: five moves

1. Approve the design once. Any certified modular design that meets the National Construction Code and the Pattern Book standards gets state approval, valid in every council. Councils assess the site, not the house. Target: 10 working days.

2. Recognise certified factories now. The national certification scheme isn’t due until mid-2028. NSW passed its own prefabricated building laws in August 2026. Use them today.

3. Guarantee the order book. Homes NSW, Landcom and the Key Worker Housing Program commit to a rolling five-year order for factory-built homes. Start with teachers, nurses and police in regional towns. The program has delivered 290 homes, 58 with modern methods (Build Australia). Make it the majority.

4. Fix the finance. Banks pay against progress on site. Factories need payment before delivery. A state-backed progress payment guarantee clears the block.

5. Build factories where people live. Require offsite methods on a share of government land releases. That creates demand for factories in western Sydney and the regions. Jobs follow.

How we’ll know it worked

  • Completions per quarter, against the Accord target
  • Days from application to approval for certified designs
  • Share of government-funded homes built offsite
  • Cost per square metre, factory versus conventional

The bottom line

I’ve spent my career in engineering and delivery. Slow building needs a better production system. Another announcement won’t help.

Empower the builders. Enable the factories. Hold everyone to the numbers.

Part of the series: Seven Problems Holding NSW Back, and a Framework to Fix Them.

Dainu Devis is Chief Executive Officer of Sharktech Global and Divine Lab Worx, its consultancy arm. He is an engineer and strategist based in Sydney.

Common questions

How many homes is NSW building compared with its target?

NSW completed 44,700 homes in the year to March 2026, according to the Property Council. Its National Housing Accord target of about 377,000 homes by mid-2029 needs more than 88,000 a year.

Are modular homes faster and cheaper to build?

Government and industry estimates say offsite construction can be up to 50 per cent faster and, at scale, up to 20 per cent cheaper. Many projects today still carry a 10 to 20 per cent premium until designs are repeated and factories have steady orders.

What is Dainu Devis's solution to the NSW housing crisis?

One approval for a certified design, valid in every council. A guaranteed multi-year order book for factory-built homes. A progress payment guarantee to fix finance. Offsite methods on government land. Quarterly public reporting on completions.